Internal / Client Organization · Project Code ERP-FOR-XYZ · 45 Working Days
| Consultant | Grade | W1 17 Nov 26 5 WD | W2 24 Nov 26 5 WD | W3 1 Dec 26 5 WD | W4 8 Dec 26 5 WD | W5 15 Dec 26 5 WD | Total | Util. |
|---|---|---|---|---|---|---|---|---|
| PM Project Manager / Delivery Lead | Project Manager / Delivery Lead | 8.3 | 3.5 | 5.6 | 7.6 | 2 | 27 | 14% |
| CRM Odoo CRM Functional Consultant | Odoo CRM Functional Consultant | 4.7 | 22.8 | 17.4 | 7.1 | 52 | 26% | |
| INT Integration & DevOps Engineer (AWS / Meta Cloud API) | Integration & DevOps Engineer | 21 | 18 | 17.1 | 2.2 | 2.7 | 61 | 30% |
| QA QA & SIT/UAT Test Analyst | QA & Test Analyst | 1.8 | 6.7 | 10.9 | 5.6 | 25 | 13% | |
| DEV Odoo Developer (build pair & dashboard) | Odoo Developer | 6.7 | 8.3 | 8 | 23 | 12% | ||
| Total team | 43 | 59 | 59 | 22 | 5 | 188 | 19% | |
| Capacity | 5 × 8 h × WD | 200 | 200 | 200 | 200 | 200 | 1,000 |
| WBS | Activity | Start | End | WD | PM | CRM | INT | QA | DEV | Hours | Basis of estimate / reasoning | Pred. |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P1 | P1 · Mobilise, AWS Environment & v19 Compatibility Gate | 7 | 6 | 30 | 4 | 9 | 56 | |||||
| 1.1 | Kickoff, scope baseline walkthrough & two remote design sessions Kickoff & Remote Design Session Pack (2 × 4h) — scope baseline, 200h burn sheet, decision log, 8-scenario acceptance outline | 4 | 2 | 2 | 1 | 0 | 9 | |||||
| 1.1.1 | Kickoff, scope baseline walkthrough & 2 remote design sessions (2 × 4h) | 17 Nov 26 | 18 Nov 26 | 2 | 4 | 2 | 2 | 1 | 9 | 2 remote sessions × (PM 2h + CRM 1h + INT 1h) = 8h + QA 1h scenario-outline review = 9h; replaces the 8 person-days of physical Amman workshops | ||
| 1.2 | Build production + staging on client AWS (me-south-1), install Odoo 19 Community, HTTPS/TLS, DNS AWS Production & Staging Environment Build Sheet + Odoo 19 Community Installation Record | 2 | 0 | 16 | 0 | 6 | 24 | |||||
| 1.2.1 | AWS me-south-1 production + staging, Odoo 19 Community install, HTTPS/TLS, DNS | 17 Nov 26 | 22 Nov 26 | 4 | 2 | 16 | 6 | 24 | 2 environments × (base build 5h + Odoo 19 Community install/hardening 3h) = 16h INT + 6h DEV scripted provisioning, TLS & DNS automation + 2h PM gate oversight = 24h | 1.1.1 | ||
| 1.3 | Daily backup cron, restore rehearsal into staging, Meta webhook reachability test Backup, Restore-Rehearsal & Webhook Reachability Evidence Log | 1 | 0 | 6 | 1 | 0 | 8 | |||||
| 1.3.1 | Daily backup cron + restore rehearsal into staging + Meta webhook reachability | 23 Nov 26 | 24 Nov 26 | 2 | 1 | 6 | 1 | 8 | Backup job 3h + 1 restore rehearsal into staging 3h = 6h INT + 1h QA evidence verification + 1h PM evidence review = 8h | 1.2.1 | ||
| 1.4 | v19 compatibility Go/No-Go gate: real module install, real WhatsApp send/receive, webhook, gate report Odoo 19 Community Compatibility Go/No-Go Report | 0 | 4 | 6 | 2 | 3 | 15 | |||||
| 1.4.1 | v19 compatibility Go/No-Go: module install on Odoo 19 Community, real WhatsApp send/receive, webhook, report | 24 Nov 26 | 26 Nov 26 | 3 | 4 | 6 | 2 | 3 | 15 | 4 fixed gate steps × 1.5h INT = 6h (module install, real send, real receive, webhook) + 3h DEV dependency/environment fixes + 4h CRM conversational-flow validation + 2h QA scripted gate test = 15h | 1.3.1 | |
| P2 | P2 · CRM Configuration, Tags & PDP Consent | 1 | 23 | 0 | 4 | 4 | 32 | |||||
| 2.1 | Configure contacts, leads, opportunities, pipeline stages, activities and ownership rules Configured Odoo CRM Core — Contacts, Leads, Opportunities, 6-Stage Pipeline, Activities & Ownership Rules | 1 | 16 | 0 | 2 | 4 | 23 | |||||
| 2.1.1 | Configure contacts, leads, opportunities, 6 pipeline stages, activities and ownership | 23 Nov 26 | 30 Nov 26 | 6 | 1 | 16 | 2 | 4 | 23 | 5 configuration blocks × 3.2h CRM = 16h (contacts, lead/opp fields, 6 stages, activities, ownership) + 4h DEV data-model & view checks + 2h QA configuration SIT + 1h PM walkthrough = 23h | 1.1.1 | |
| 2.2 | Create project + unit-type standard tags and two saved filters/group-bys Tag Taxonomy (Project × Unit Type) & Saved Filter Specification | 0 | 4 | 0 | 1 | 0 | 5 | |||||
| 2.2.1 | Project + unit-type standard tags and two saved filters/group-bys | 30 Nov 26 | 1 Dec 26 | 2 | 4 | 1 | 5 | 2–3 projects × unit types = 12 tags + 2 saved filters = 4h CRM + 1h QA verification = 5h; standard tags instead of custom fields → 0h custom development | 2.1.1 | |||
| 2.3 | PDP Law consent capture field + consent tag (client owns wording and records) and cross-border annex support Consent Capture Field, Consent Tag & PDP Law Documentation Note (incl. me-south-1 cross-border annex) | 0 | 3 | 0 | 1 | 0 | 4 | |||||
| 2.3.1 | PDP consent field + consent tag (client owns wording/records) and cross-border annex support | 30 Nov 26 | 1 Dec 26 | 2 | 3 | 1 | 4 | Consent field + tag + evidence note 3h CRM (client supplies wording and retains records) + 1h QA spot-check of 10 records = 4h; cross-border annex is a client-signed document with 0 build hours | 2.1.1 | |||
| P3 | P3 · WhatsApp Cloud API, Templates & Dashboard | 1 | 13 | 25 | 4 | 10 | 53 | |||||
| 3.1 | Connect WhatsApp Cloud API from the client's own Meta account and deliver the single shared conversation view Live WhatsApp Cloud API Channel + Single Shared Conversation View (5 seats) | 1 | 4 | 18 | 3 | 4 | 30 | |||||
| 3.1.1 | WhatsApp Cloud API from client Meta account + single shared conversation view (5 seats) | 26 Nov 26 | 3 Dec 26 | 6 | 1 | 4 | 18 | 3 | 4 | 30 | Meta app config 5h + webhook endpoint hardening 5h + inbox/assignment wiring 6h + multi-seat test 2h = 18h INT + 4h DEV + 4h CRM conversation-to-lead mapping + 3h QA end-to-end send/receive across 5 seats + 1h PM channel acceptance = 30h | 1.4.1 |
| 3.2 | Draft, submit and wire the 2 bilingual templates (welcome/acknowledgement + appointment confirmation) Two Meta-Approved Bilingual WhatsApp Templates, Wired and Live-Tested | 0 | 7 | 7 | 1 | 0 | 15 | |||||
| 3.2.1 | Draft, submit and wire 2 bilingual templates (welcome/acknowledgement + appointment confirmation) | 1 Dec 26 | 3 Dec 26 | 3 | 7 | 7 | 1 | 15 | 2 templates × 2 languages = 4 variants × 2h drafting & submission = 8h CRM + 7h INT variable mapping and live send test + 1h QA approval regression = 15h (attribute 1h of drafting to QA-supported review) | 3.1.1 | ||
| 3.3 | Build the single sales-funnel dashboard by source and channel with written metric definitions Sales Funnel Dashboard by Source & Channel + Written Metric Definitions | 0 | 2 | 0 | 0 | 6 | 8 | |||||
| 3.3.1 | One sales-funnel dashboard by source and channel with written metric definitions | 3 Dec 26 | 7 Dec 26 | 3 | 2 | 6 | 8 | Standard pivot/graph funnel: data-model check 2h + funnel view 3h + source/channel splits 2h + metric definitions 1h = 6h DEV + 2h CRM definitions review = 8h (built on standard views to hold the 200h ceiling) | 2.2.1,3.1.1 | |||
| P4 | P4 · Smoke Acceptance, Bilingual Docs & Handover | 18 | 10 | 6 | 13 | 0 | 47 | |||||
| 4.1 | Write 8 smoke-acceptance scenarios before build, execute SIT/UAT, log defects and obtain sign-off 8 Smoke-Acceptance Scenarios, SIT/UAT Execution Log & Signed Acceptance Record | 6 | 5 | 2 | 13 | 0 | 26 | |||||
| 4.1.1 | Author 8 smoke scenarios before build, execute SIT/UAT (3-day structured sprint), log defects, obtain sign-off | 2 Dec 26 | 10 Dec 26 | 7 | 6 | 5 | 2 | 13 | 26 | 8 scenarios × 0.75h authoring (PM 3h + CRM 3h) + 3-day UAT execution sprint 13h QA + 2h CRM + 2h INT technical triage + 3h PM defect log & sign-off = 26h | 3.2.1 | |
| 4.2 | Deliver abbreviated bilingual AR/EN guide, quick-reference card and one bilingual training session Abbreviated Bilingual AR/EN User Guide (5 journeys), Quick-Reference Card & One Training Session with Evaluation | 3 | 5 | 0 | 0 | 0 | 8 | |||||
| 4.2.1 | Abbreviated bilingual AR/EN guide (5 journeys) + quick-reference card + one bilingual training session | 9 Dec 26 | 14 Dec 26 | 4 | 3 | 5 | 8 | 5 journeys × 0.6h = 3h CRM drafting + AR/EN parity & A4 quick-reference card 2h CRM + one 3h bilingual training session (PM 1h delivery + 2h preparation/evaluation) = 8h | 4.1.1 | |||
| 4.3 | Write AWS Runbook (restore, patching calendar, escalation, responsibility matrix) and close-out report AWS Operations Runbook & Pilot Close-out Report with Responsibility Matrix | 1 | 0 | 4 | 0 | 0 | 5 | |||||
| 4.3.1 | AWS Runbook (restore, patching calendar, escalation, responsibility matrix) + close-out report | 14 Dec 26 | 16 Dec 26 | 3 | 1 | 4 | 5 | Runbook 4h INT (restore, patching calendar, escalation, IAM/root responsibility matrix) + 1h PM close-out reconciliation against the 200h ceiling = 5h | 4.1.1 | |||
| 4.4 | Weekly status, change control, decision log and gate oversight across the 200h ceiling Weekly Status Pack, Change Control Log & Gate Tracker (200h burn) | 8 | 0 | 0 | 0 | 0 | 8 | |||||
| 4.4.1 | Weekly status, change control, decision log and gate oversight across the 200h ceiling | 17 Nov 26 | 20 Dec 26 | 24 | 8 | 8 | 5 weekly cycles × 1.6h = 8h PM (status pack, burn vs 200h, change log, gate tracking); remaining governance hours embedded in tasks 1.1 / 2.1 / 4.1 / 4.3 | |||||
| TOTAL | 27 | 52 | 61 | 25 | 23 | 188 | ||||||
| Role / Grade | Headcount | LoE Hours | h / member | Util. (of 200 h) |
|---|---|---|---|---|
| Project Manager / Delivery Lead | 1 | 27 | 27 | 14% |
| Odoo CRM Functional Consultant | 1 | 52 | 52 | 26% |
| Integration & DevOps Engineer | 1 | 61 | 61 | 31% |
| QA & Test Analyst | 1 | 25 | 25 | 13% |
| Odoo Developer | 1 | 23 | 23 | 12% |
| Total | 5 | 188 | 38 | 19% |
| Date | Event | Type |
|---|---|---|
| 17 Nov 26 | Client: AWS account, root IAM contact and Meta Business Manager app access provisioned | Milestone / gate |
| 19 Nov 26 | G1 · Design & scope baseline sign-off (2 WD SLA) (until 22 Nov 26) | Client review |
| 2 Dec 26 | Client: 2 bilingual templates submitted to Meta + PDP consent wording + me-south-1 cross-border annex signed | Milestone / gate |
| 8 Dec 26 | Client: 100–150 active records entered via Agile template with consent captured | Milestone / gate |
| 17 Dec 26 | G2 · Smoke acceptance sign-off (2 WD SLA) (until 20 Dec 26) | Client review |
| 25 Dec 26 | Christmas Day (Jordan) | Public holiday (non-working) |